試卷名稱:111年 - 111 學士後醫學系招生考試:計算機概論與程式設計#107630
年份:111年
科目:學士後西醫◆計算機概論與程式設計
17. Consider five processes as follows. They arrived in the order of P1, P2, P3, P4, and P5 at time 0. What is the total turnaround time of all processes by using the shortest-job-first (SJF) scheduling algorithm?
(A) 25
(B) 30
(C) 35
(D) 40
(E) 45